>Daily Development for Friday, August 15,
2008
>by: Patrick A. Randolph,
Jr.
>Elmer F. Pierson Professor of
Law
>UMKC School of Law
>Of Counsel: Husch Blackwell Sanders
>Kansas City, Missouri
>dirt@umkc.edu
>
>Here’s another great contribution from Dale
Whitman:
>
>MORTGAGES; SUBROGATION; CONSTRUCTION LOANS: A permanent
mortgage may not claim subrogation to a construction mortgage in order to gain
priority over an intervening mechanics lien.
>
>Lawson v. Brian
Homes, Inc., 2008 WESTLAW 2780780 (Ala. Jul. 18, 2008) (not yet released for
publication)
>
>This case presents a simple but challenging fact pattern. Brian Homes
built houses in a subdivision, financing the work with a construction loan
obtained in 2003 from New South Federal Savings Bank, whose mortgage was
properly recorded. During the course of construction, Brian hired Lawson to
perform work on the houses. Brain failed to pay Lawson for her work. In January
2004 the completed homes were sold, and the buyers all obtained “permanent”
loans from other lenders. After these closings occurred, but within the time
allowed by the Alabama mechanics lien statute, Lawson recorded a notice of
mechanics lien.
>
>The Alabama
mechanics lien statute gives mechanics liens a priority date as of the date work
commences on the project, and provides that liens are subordinate to mortgages
recorded before work commences. However, it states that mechanics liens have
priority over mortgages created after work commences. Ala. Code
35-11-211.
>
>On the face of
things, the permanent loans would appear to be subordinate to the mechanics
liens, which is what Lawson argued. However, the permanent lenders claimed that
they should be subrogated to the priority of the construction loan, which they
had paid off, and hence gain priority over the liens. The Alabama Supreme Court
ultimately rejected the subrogation argument and held that, under the statute,
the liens had priority.
>
>The court employed
three arguments in rejecting subrogation, each of which is discussed
below:
>
>1. The “same debtor” argument. The court quoted prior Alabama case
law that had held the first element of equitable subrogation was that “the money
is advanced at the instance of the debtor in order to extinguish a prior
incumbrance.” In the present case, the court observed that the money advanced by
the permanent lenders was lent not at the request of the original debtor (Brian
Homes) but at the request of the individual buyers who were purchasing the
homes.
>
>This is a rather
mechanistic argument, but it raises a genuine policy issue: should subrogation
be available for a refinancing in connection with a purchase of the property, or
only when there is a refinancing by the same owner? There is surprisingly little
discussion of this issue in the cases. Several recent cases have granted
subrogation in the context of a sale of the property and new financing by the
new owner. See In re Project Homestead, Inc., 374 B.R. 193 (Bkrtcy.M.D.N.C.
2007); Ocwen Loan Servicing, LLC v. Williams, 305 Wis.2d 772, 741 N.W.2d 474
(Wis.App.2007); Decaro v. M. Felix, Inc., 371 Ill.App.3d 1103, 864 N.E.2d 890
(Il.App. 1 Dist.,2007). But none of these cases appear to recognize that the
issue is controversial or attempt any serious discussion of it. I’m aware of
only one case that does: E. Boston Sav. Bank v. Ogan, 701 N.E.2d 331 (Mass.
1998), where the court said:
>Because we find that the equities are substantially similar in refinancing and sales transactions, and that application of equitable subrogation to a sale is consistent with our precedent, we hold that equitable subrogation applies in this case. ... [T]he distinction between a sale and a refinancing exists, but subrogation arising out of either context yields the same result.
>
>For what it’s
worth, the Restatement expressly includes sale transactions within its
definition of subrogation; Rest. (Third) of Property (Mortgages) §7.6(b)(4)
speaks of a payment of a mortgage “upon a request from the obligor or the
obligor's successor to do so.” (italics added)
>
>The bottom line is
that the Alabama court in Lawson applied the “same debtor” argument mechanically
and without giving any reason that it ought to be the rule. In this respect, the
opinion is weak and unconvincing.
>
>2. The lender must
be ignorant of the intervening lien. The court held that subrogation will only
be available where the refinancing lender lacks notice of the intervening lien.
Prior Alabama case had held that anyone who buys a new building “has
constructive notice that material used to build the structure may not be paid
for,” and therefore has notice that there may be a mechanics lien filed on the
property.
>Since this sort of notice always exists when the intervening lien is a mechanics lien, it is tantamount to saying that no lender can ever use subrogation to gain priority over a mechanics lien. Of course, the real culprit here is the basic structure of the lien law, which allows the lien claimant to file up to 6 months (for general contractors) or 4 months (for subcontractors and materials suppliers) after the last item of work on the project has been completed. (Ala. Code §35-11-215) Thus, for a period of up to 6 months, the impending lien can be secret, and impossible to find by any title search.
>
>This is, of
course, outrageous in terms of public policy, but it is well-established in
Alabama and many other states. Contractors, lumber yards, and others in the
construction business love it. It has the effect of making buyers and their
lenders responsible for the unpaid bills of the builders of newly-constructed
real estate. There is no satisfactory way that buyers and their lenders can
guard against this risk. Getting lien waivers is fine as far as it goes, but
it’s impossible to be sure that all of the people who have supplied labor or
materials have signed waivers. One might buy title insurance against the risk,
but many title policies sold don’t cover it. Because some policies do, it is the
largest single source of title insurance claims. It’s difficult to believe that
a civilized society puts up with this sort of rule, but we do.
>
>Rant over! Alabama
has made its choice on this point. And if buyers and their lenders are generally
subject to intervening (and secret) mechanics liens, why should the doctrine of
subrogation bail them out? That seems to be the court’s position: the statute
says that later lenders are the losers, and by golly, they’re
losers!
>
>3. Subrogation to
a construction loan would be unfair to the intervening lienor. This third
argument against subrogation was made only by the concurring opinion of Justice
Lyons, but it may be the most persuasive. Everyone agrees that subrogation is
proper only if it will (in the Restatement’s words) “not materially prejudice
the holders of intervening interests.” If subrogation is granted, the mechanics
lien claimant, who was previously subordinate only to a short-term construction
loan, will now be subordinate to a 20-year or 30-year permanent loan. That sort
of switch, the argument goes, is detrimental to the lien claimant. This argument
makes some sense. If the construction loan had gone unpaid, it would likely have
been foreclosed quickly. With a long-term loan as a substitute, it’s likely that
the borrower will make the payments and no foreclosure by the senior lender will
ever occur. The lien claimant can foreclose the lien, of course, but if it’s
subject to a senior mortg
age for a large amount, maybe foreclosure of the lien will
produce little or nothing to pay the lien.
>
>Reporter’s Comment 1: Bob
Harris, a very experienced Alabama lawyers who filed a brief in the case arguing
against subrogation, made the following additional argument in an e-mail to
me.
>
>It has long been
my view that the dynamics of a construction loan mortgage situation are quite
different from those involved in conventional permanent lending. Typically
the construction lender loans a lower percentage of the expected improvement
value and the loan term is much shorter. Also, typically an ongoing
business relationship exists between a construction lender and a developer that
does not exist where a lender makes a long term loan to a home buyer. Even
threats of prosecution by unpaid contractors against a construction loan
borrower frequently cause the developer to find funds and either pay the
contractors or satisfy the construction lender so that a release of the property
subject to a lien is given. These considerations are taken into account by
a material supplier when asked to extend credit to a developer; and while the
supplier may be willing to extend credit subordinate to the construction loan
mortgage that same supplier would not extend the credit as subo
rdinate to a mortgage given to a permanent mortgage lender.
>
>Thus, I would argue that the Restatement Subrogation view should not
be applicable to a "refinancing" by a permanent loan borrower of a debt secured
by an earlier construction loan debtor, where there are intervening statutory
liens. Indeed, I do not think the buyer of a new residence who gives a mortgage
to secure funds with which to purchase a house, a part of which is paid to
secure the release of a lot from a construction loan mortgage, can in any
legitimate sense be regarded as "refinancing" the construction loan
debt.
>
>I’d be interested
in whether DIRT readers find these argument convincing. If you represented a
mechanics lien claimant, would you rather be subordinate to a construction loan
than a long-term loan?
>
>Reporter’s
Comment: 2: The court says that its position is approved by an illustration in
the Restatement, but that’s not quite accurate. The illustration, which is in
Restatement s7.6, comment f, involves a different fact pattern, one in which
there is a delay of a few days between the satisfaction of the old construction
mortgage and the recording of the new long-term mortgage, and the work of
construction commences during that period of delay. The illustration says the
court is justified in refusing to grant subrogation because it would unjust to
the lien claimant to do so. That’s true, of course, because when the lien
claimant commenced construction, the public records would have indicated that
there was no prior mortgage on the property. But it’s quite different from
Lawson, in which the lien claimant knew full well, when she did the work on the
land, that there was a construction loan that would have priority over any lien
that might be filed. In effect, Lawson holds that t
he lien claimant “lucked out” by virtue of the fact that the
construction loan was replaced by a permanent loan.
>
>Editor’s Comment 1: This case
illustrates a very important point that the editor, candidly, has lost sight of,
assuming he ever knew it. The subrogated position has the priority of the
old loan, but the terms and conditions of the new loan, at least insofar as the
equities are appropriate. And if, as here (see the third argument above),
the equities are inappropriate, subrogation is denied entirely.
>
>The editor
certainly, in his ruminations about this before, has speculated that the
subrogating loan not only gets priority as to the original loan, but also the
terms and conditions of that earlier loan. Apparently, according to Dale,
after research, this is not the situation. The court will install the new
loan (up to the amount paid to the earlier loan) on the new loan’s terms, so
long as not equitably injurious. Since the editor has researched the
question of whether a mortgagor and mortgagee can modify a loan (even without a
provision so permitting) and has generally concluded that they can, this is not
a surprising result. But what is interesting is that if the court should
conclude that giving the new lender’s terms priority is not equitable, it
apparently will not elect to give the new lender the old lender’s terms.
It will just deny subrogation entirely.
>
>In the instant
case, where the construction loan probably had passed its due date and had been
paid off by the individual mortgage loans to the purchasers, it would not have
made any sense to grant subrogation to an expired loan on its
terms.
>
>Editor’s Comment
2: The editor has always found inappropriate the granting of equitable relief to
one who walks into the “inequitable situation” with eyes open. Thus, the
editor does not agree with the Restatement notion that parties can be subrogated
to senior liens over intervening even when the party paying the senior lien is
aware of the intervening liens.
>
>The editor agrees
further with Bob Harris that there are significant differences between the
relationship of a construction lender to a developer and a permanent lender to a
home buyer that makes it nearly impossible to conclude that the “equities are
equal” in evaluating whether to grant subrogation.
>
>
>
>The Reporter for
this item was Dale Whitman of the Missouri, Columbia Law School, emeritus.
>
>Readers are encouraged to respond to or criticize this
posting.
>
>Items reported on DIRT and in the ABA publications related to
it are for general information purposes only and should not be relied upon
in the course of representation or in the forming of decisions in legal
matters. The same is true of all commentary provided by contributors to
the DIRT list. Accuracy of data provided and opinions expressed by
the DIRT editor the sole responsibility of the DIRT editor and are in no sense
the publication of the ABA.
>
>
>Parties posting messages to DIRT are posting to
a
>source that is readily accessible by
members of
>the general public, and should
take that fact
>into account in evaluating
confidentiality
>issues.
>
>ABOUT
DIRT:
>
>DIRT is an internet discussion group for serious
>real estate professionals. Message volume
varies,
>but commonly runs 5 - 15 messages
per work day.
>
>Daily Developments are posted every work day. To
>subscribe, send the message
>
>subscribe Dirt [your
name]
>
>to
>
>listserv@listserv.umkc.edu
>
>To cancel your subscription,
send the message
>signoff DIRT to the
address:
>
>listserv@listserv.umkc.edu
>
>for information on other
commands, send the message
>Help to the
listserv address.
>
>DIRT has an alternate, more extensive coverage that
includes not only
>commercial and general
real estate matters but also focuses upon residential real estate matters.
Because real estate brokers generally find this service more valuable, it is
named “BrokerDIRT.” But residential specialist attorneys, title insurers,
lenders and others interested in the residential market will want to subscribe
to this alternative list. If you subscribe to BrokerDIRT, it is not
necessary also to subscribe to DIRT, as BrokerDIRT carries all DIRT traffic in
addition to the residential discussions.
>
>To subscribe to
BrokerDIRT, send the message
>
>subscribe BrokerDIRT [your name]
>
>to
>
>listserv@listserv.umkc.edu
>
>To cancel your subscription to
BrokerDIRT, send the message
>signoff
BrokerDIRT to the address:
>
>listserv@listserv.umkc.edu
>
>DIRT is a service of the
American Bar Association
>Section on Real
Property, Probate & Trust Law and
>the
University of Missouri, Kansas City, School
>of Law. Daily Developments are copyrighted by
>Patrick A. Randolph, Jr., Professor of Law,
UMKC
>School of Law, but Professor Randolph
grants
>permission for copying or
distribution of Daily
>Developments for
educational purposes, including
>professional continuing education, provided that
>no charge is imposed for such distribution
and
>that appropriate credit is given to
Professor
>Randolph, DIRT, and its
sponsors.
>
>DIRT has a WebPage at:
>https://e2k.exchange.umkc.edu/exchweb/bin/redir.asp?URL=http://www.umkc.edu/dirt/
>
>Members of the
ABA Section on Real Property, Probate
>and
Trust Law or of the National Association of Realtors can subscribe to a
quarterly hardcopy report that includes all DIRT Daily Developments, many other
cases, and periodic reviews of real estate oriented literature and state
legislation by contacting Antonette Smith at (312) 988 5260 or
asmith4@staff.abanet.org