Daily
Development for Tuesday, August 3, 1999
By:
Patrick A. Randolph, Jr.
Professor of Law
UMKC School of Law
Of Counsel: Blackwell Sanders Peper Martin
Kansas City, Missouri
randolphp@umkc.edu
VENDOR/PURCHASER;
EXTENSIONS: Contract extension agreement, contingent upon buyer's deposit of
additional earnest money, is a valid independent agreement to extend the time
for closing, and buyer cannot "backtrack" to original closing date
simply by failing to produce the agreed upon additional earnest money.
Sage
Technology, Inc. v. Nationsbank N.A. South, 509 S.E.2d 694 (Ga. App. 1998).
Buyer
agreed to buy certain land from Seller for $1.8 million. Over time, Buyer put
up $100,000 in forfeitable earnest money payments. There were defects in title,
of which Buyer was aware, and the parties agreed that Seller would produce a
"limited warranty deed," (a term unfamiliar to the editor). The
contract had a "time of essence" clause."
Although,
according to the court, the nature of the deed stipulated by the parties did
not require Seller to have good title, there apparently was a good deal of
discussion about title defects and Seller agreed to cure certain of these
defects. A few days before scheduled closing, the parties agreed in writing to
extend the closing for an additional month, and Buyer was required to make an
additional payment of earnest money in the amount of $25,000 within two days of
the extension agreement.
Buyer
alleged that, after the signing of this agreement, it discovered that Seller
had withheld information concerning certain defects in title that had been
"papered over" and Buyer therefore refused to put up the additional
money.
Seller
declared the contract terminated due to the failure to pay the additional
earnest money and sought to retain the earnest money. Buyer sued for its
return. Trial court granted summary judgment for Seller, and Buyer appealed.
On
appeal: held: Affirmed. The most interesting element of Buyer's argument was
the claim that the extension agreement constituted an option on the part of
Buyer to extend the contract by paying additional earnest money or to demand
simply that Seller perform on the original date. As it didn't pay the money,
Buyer claimed, the original contract terms were binding, and Seller could not
declare Buyer in breach because Seller was not in a position to deliver good
title as agreed.
Although,
as noted, the court elsewhere holds that Seller did satisfy whatever title
requirements existed, the court appears to assume here, for purposes of
argument, that Buyer's claim that Seller couldn't close on the original date
was accurate. The court nevertheless concludes that Buyer's defense is
insufficient, because the original date was irrevocably altered by the
extension agreement, which became binding not as a consequence of the actual
payment of the additional earnest money, but by Buyer's promise to pay that
money within 48 hours.
The
court also rejected the buyer's argument that the extension agreement didn't
require timely performance because it didn't include a "time of essence
clause" or a forfeiture provision. Where the amendment modified only the
closing date and not the provisions regarding the earnest money deposit in the
event of default, the original provisions with respect to still controlled time
of essence and earnest money forfeiture still controlled.
Comment
1: The editor is curious about the "limited warranty deed" in Georgia
and why this device insulated Seller from a requirement of marketable title.
Comment
2: The court obviously viewed the Buyer as a defaulter scrambling to recoup
from a deserved consequences, and the interpretation of the extension agreement
should be read in that light. But the editor includes the case as a Daily
Development as a drafter's warning. Clearly it might be possible for a party
with an extension right triggered by a payment of an additional earnest money
to view this right as an option, and not as a binding performance obligation.
The court doesn't so construe the arrangement here, emphasizing that clarity of
drafting is vital in these cases. Last minute "patch ups" often do
not adequately anticipate possible changes in circumstance as well as the
original contract language, which was drafted with more time and thought. A
good drafter who is aware of the danger of drafting under pressure will recognize
the tendency in such situations to plan only for the anticipated course of
events, and to ignore other possibilities, and will resist that tendency as
much as negotiations comfortably permit.
Items
in the Daily Development section generally are extracted from the Quarterly
Report on Developments in Real Estate Law, published by the ABA Section on Real
Property, Probate & Trust Law. Subscriptions to the Quarterly Report are
available to Section members only. The cost is nominal. For the last six years,
these Reports have been collated, updated, indexed and bound into an Annual
Survey of Developments in Real Estate Law, volumes 16, published by the ABA
Press. The Annual Survey volumes are available for sale to the public. For the
Report or the Survey, contact Maria Tabor at the ABA. (312) 988 5590 or
mtabor@staff.abanet.org
Items
reported here and in the ABA publications are for general information purposes
only and should not be relied upon in the course of representation or in the
forming of decisions in legal matters. The same is true of all commentary
provided by contributors to the DIRT list. Accuracy of data and opinions
expressed are the sole responsibility of the DIRT editor and are in no sense
the publication of the ABA.