Daily Development for Monday, November 29,
1999
By:
Patrick A. Randolph, Jr.
Professor of Law
UMKC School of Law
Of Counsel: Blackwell Sanders Peper Martin
Kansas City, Missouri
randolphp@umkc.edu
Thanks to the indefatigable H.E. Peterson
for the tip on this one:
INSURANCE; STATUTE OF LIMITATIONS;
LIMITATIONS; CONTRACTUAL LIMITS: Provisions in property insurance policy limiting
period during which suit can be brought to two years from occurrence of injury
is valid not only to shorten limitations period but also to alter the event
from which the limitations period is measured by eliminating application of the
"discovery rule."
Caln Village Associates v. the Home
Indemnity Company, http://www.paed.uscourts.gov/opinions/99D0951P.HTM,
(E.D. Penn. 11/23/99)
Owners of a shopping center completed in
1991 observed some cracks in the foundation within one year of completion of
construction. The owners included this
problem included on "punch lists" of completion items under
discussion with contractor for some time, and eventually it became a major item
in their discussions. The parties described the problem as a "settlement
problem," but eventually it was diagnosed as related to inadequately cured
slag used as fill beneath the foundation. This material chemically altered its
nature and, as altered, was subject to expansion, which not only caused cracks
in the foundation but also problems with window sills, doors, and even breaking
glass.
In Spring of 1994, the contractor had
diagnosed the problem as a problem with the slag. But as of July, 1994, the
contractor wrote to the owners and to indicate its tentative diagnosis. The contractor advised the owners not to
bring in experts to evaluate the problem and propose a solution. The contractor did, however, advise the
owners "that it was extremely important to put the various subcontractors
and insurance company [sic] on notice of the problem."
By December of 1994, however, with problems
getting worse, the owners did bring in expert consultants, and brought in more
consultants the following spring. The consultants concluded that the only
practical solution was removing the fill from beneath the foundation and replacing
it - obviously an extremely expensive "fix," and one which would
likely interrupt shopping center operations.
The owners sued the contractor for
negligence and related claims in April of 1996, and six months later added various
insurance companies that had insured the property against property damage
during the relevant period.
The insurers based their defense upon the
fact that the owners had brought their lawsuit against the insurers too late. All
three policies contained a suit limitation clause which states that no legal
action could be brought unless the action was "brought within 2 years
after the date on which the direct physical loss or damage occurred."
The owners defended on the grounds that the
two year limitation was unreasonable, that if it was enforceable, the insurers
were required to show prejudice from delay in order to invoke it, and that in
any event two years had not run from the time the problem was
"discovered" within the meaning of the "discovery rule"
commonly applied to statutes of limitations.
The District Court here granted summary
judgment to the insurers.
In response to the claim that the provision
was unreasonable, the court simply invoked a statute in Pennsylvania holding
that contractual limitations on suit that narrow the statute of limitations
that would otherwise apply are perfectly valid so long as they are not
"manifestly unreasonable." As Pennsylvania law places a one year
statute of limitations on some claims against fire insurers, the court
concluded that the two year limit contained in the provisions at issue here
were not "manifestly unreasonable" by Pennsylvania standards, even
though they cut the time for suit in half.
As to the question of whether the insurers
had to demonstrate that they were prejudiced by the delay, the court
acknowledged some uncertainty in Pennsylvania authority. Prior authority had
held definitely that an insurer had to show prejudice in order to defend on the
basis of late notification of a claim, and the court noted some Pennsylvania
authority extending the concept to limitations provisions. But other, more
recent, authority declined to extend the doctrine to limitations provisions,
and the court concludes, without analyzing policy considerations, that this is now
Pennsylvania law. No prejudice need by shown.
The next issue was whether indeed two years
had run since the an "occurrence" within the meaning of the policies.
The owners argued that the injury they were suffering was ongoing and
manifested in a variety of ways. Consequently, as applied to their situation,
the term "occurrence" was ambiguous, and they were entitled to a
generous construction.
The court agreed to the extent that it
acknowledged that until it was clear that something in the foundation was
causing the problems, rather than simply settlement, there could have been no
"occurrence" of an injury. Nevertheless, in the court's view it was
not necessary for the owners to receive an exact report from their engineering
consultants in order for there to have been an occurrence of an injury:
"ertainly
by July 28, 1994, when Caln Village learned that the problems at Caln Village
were consistent with the expansion of un-cured slag, a reasonable person would have
been on notice that the problems at Caln Village were not
due to normal settling but the result of an injury due to expanding
un-cured slag. For the same reason, even if a jury could draw an
inference from the record that Caln Village was not put on
notice by the persistent and progressive nature of the problems
because it believed that the problems were due to normal settling, the
last possible day on which the limitations period could begin is
July 28, 1994. Again, by July 28, 1994, it is uncontroverted that
Caln Village was on notice that the problems at the shopping
center were not due to normal settling but the result of an injury
due to expanding un-cured slag. By then Caln Village not only
had knowledge of the problems and the extent of the problems
but also the possible cause of the problem and thus was on notice
of the injury such that the limitations period began to run.
Based upon the evidence presented, a reasonable jury could not find
otherwise."
The court went on to find that the
"discovery rule" that might apply in Pennsylvania absent contractual
definitions of the running of a limitations provision did not apply here. But
it also held that if the discovery rule did apply, the above analysis
demonstrated that the problem had been "discovered" by July of 1994.
Comment 1: Obviously there are important
counseling lessons here for attornies advising clients when dealing with
construction defects. Some such defects are covered by property insurance, but
the insurance policies frequently contain limitations that severely truncate
the running of the statute of limitations.
It is most important to note that these
provisions are separate and apart from the notice provisions. You may have
notified the insurer. The owners in this case undoubtedly did so - having been
specifically advised by their contractor. But that is not enough to satisfy the
limitations restriction. You must file suit, often much earlier than one might otherwise
deem necessary.
Undoubtedly what was going on here was the
normal pre litigation wrangling with the contractors who were the real targets
of the owner's ire. The attornies involved simply failed to recognize that a
substantial claim might be lost if this wrangling extended for too long.
Comment 2: Missing a statute of limitations
is a virtual "pat hand" when it comes to malpractice claims. Should
the same rule apply to these special limitations for claims against insurers? It's
a tough standard, but that's why we make the big bucks. Right? (The editor
acknowledges that here a malpractice claim might not succeed until it is shown
that the claims against the contractor don't pan out.)
Comment 3: The editor is hostile to
overreaching provisions in form insurance policies, and would apply a prejudice
requirement to invoke a limitation on suit. After all, the insurer (presumably)
has been named and evidence can be preserved. What's the big rush?
Readers are urged to respond, comment,
and argue with the daily development or the editor's comments about it.
Items in the Daily Development section
generally are extracted from the Quarterly Report on Developments in Real
Estate Law, published by the ABA Section on Real Property, Probate & Trust
Law. Subscriptions to the Quarterly Report are available to Section members
only. The cost is nominal. For the last six years, these Reports have been
collated, updated, indexed and bound into an Annual Survey of Developments in
Real Estate Law, volumes 1‑6, published by the ABA Press. The Annual
Survey volumes are available for sale to the public. For the Report or the
Survey, contact Maria Tabor at the ABA. (312) 988 5590 or
mtabor@staff.abanet.org
Items reported here and in the ABA
publications are for general information purposes only and should not be relied
upon in the course of representation or in the forming of decisions in legal
matters. The same is true of all commentary provided by contributors to the DIRT
list. Accuracy of data and opinions expressed are the sole responsibility of
the DIRT editor and are in no sense the publication of the ABA.
Parties posting messages to DIRT are posting
to a source that is readily accessible by members of the general public, and
should take that fact into account in evaluating confidentiality issues.
ABOUT DIRT:
DIRT is an Internet discussion group for
serious real estate professionals. Message volume varies, but commonly runs 5 ‑
10 messages per workday.
Daily Developments are posted every workday.
To subscribe to Dirt, send an e-mail to:
To: |
ListServ@listserv.umkc.edu |
Subject: |
[Does not matter] |
Text in body of message |
Subscribe Dirt [your name] |
To cancel your subscription to Dirt, send an
e-mail to:
To: |
ListServ@listserv.umkc.edu |
Subject: |
[Does not matter] |
Text in body of message |
Signoff Dirt |
For information on other commands, send the
message Help to the listserv address.
DIRT has an alternate, more extensive
coverage that includes not only commercial and general real estate matters but
also focuses specifically upon residential real estate matters. Because real
estate brokers generally find this service more valuable, it is named
“Brokerdirt.” But residential specialist attorneys, title insurers, lenders and
others interested in the residential market will want to subscribe to this
alternative list. If you subscribe to Brokerdirt, it is not necessary also to
subscribe to DIRT, as Brokerdirt carries all DIRT traffic in addition to the
residential discussions.
To subscribe to Brokerdirt, send an e-mail
to:
To: |
ListServ@listserv.umkc.edu |
Subject: |
[Does not matter] |
Text in body of message |
Subscribe Brokerdirt [your name] |
To cancel your subscription to Brokerdirt,
send an e-mail to:
To: |
ListServ@listserv.umkc.edu |
Subject: |
[Does not matter] |
Text in body of message |
Signoff Brokerdirt |
DIRT is a service of the American Bar
Association Section on Real Property, Probate & Trust Law and the
University of Missouri, Kansas City, School of Law. Daily Developments are
copyrighted by Patrick A. Randolph, Jr., Professor of Law, UMKC School of Law,
but Professor Randolph grants permission for copying or distribution of Daily
Developments for educational purposes, including professional continuing
education, provided that no charge is imposed for such distribution and that
appropriate credit is given to Professor Randolph, DIRT, and its sponsors.
DIRT has a WebPage at:
http://www.umkc.edu/dirt/